COMPLEX OF WORKS ON CONSTRUCTION, RECONSTRUCTION AND MODERNIZATION

Construction and installation companies SMIT perform a range of works on the construction, reconstruction and modernization of heating networks.

High-quality installation of pipelines and the performance of special operations guarantee the absence of problems during their operation.

High quality of construction and installation works means reliability, long service life and safety of your pipelines

We provide a range of engineering services, including the development of project documentation, the production of pipes and the installation of heating mains.

The rich technical and practical experience of our team allows us to quickly solve the most complex problems.

SMIT Group was entrusted with participation in such important construction works as preparation for the celebration of the 1150th anniversary of the city of Smolensk and preparation for the 2014 Olympics in Sochi.

FEATURES OF INSTALLATION OF PIPELINES:

The channelless method of building a heating main is the most cost-effective way of laying a pipeline. With this method, the construction of special structures for laying the pipeline is not required. The heating main is laid directly into the ground with a sand base at least 150 mm thick and sandy at least 150 mm above the jacket pipe.

  • The device of serviced thermal chambers with channelless laying, as a rule, is not required.

Pipes insulated with polyurethane foam should be lowered into the trench smoothly, without jerks and impacts on the walls and bottom of channels and trenches on a specially prepared sandy base.

MANDATORY TO CHECK:

  • Electrical resistance SODK
  • Integrity of signal wires SODK

Integrity of signal wires SODK

When welding individual sections of pipes, it is necessary to provide protection
protruding areas of foam from welding spatter using special screens.

A heat-shrinkable sleeve is installed near each pipe joint before the weld is made. At the same time, it must be ensured
the integrity of the protective shell of the coupling, to prevent its shrinkage before sealing the joint under the action of sunlight and external damage.

Interpipe joints are insulated using the supplied
joint sealing kits. Before pouring the PPU components, it is checked
tightness of the connection of the heat-shrinkable sleeve and the polyethylene sheath by crimping at a pressure of 0.5 bar for 5 minutes.

Before carrying out backfilling at the corners of rotation, in the area of movement of n-, Z-, L-shaped compensators, as well as in the area of the location of tee branches, expansion mats made of foamed polyethylene must be installed. The length of the lining zones with mats and their thickness depend on the magnitude of temperature elongations in the sections of the pipeline and are determined by the project.

After completion of the installation of the pipeline and SODK, carrying out acceptance hydraulic tests, a control reflectogram of the state of PPU insulation is taken, which is part of the as-built documentation.